Clarifiers

Altamonte Springs WRF Phase I & II Maitland, FL

Install four 90' Clarifiers with coatings and new equipment. Demolish existing clarifiers. Install two precast manholes, one for the new chemical building and one for the new clarifiers.

Make modifications to the existing nitrifications tanks. Demo existing clarifier equipment and pour new walls to separate into anoxic and reaeration tanks. Installed stainless steel piping, big bubble diffusers, and fine bubble diffusers.

Build a new splitter box with four weir slide gates and build a new scum box with telescoping valves for the four clarifiers and install two submersible pumps in the scum box.

Run new underground and aboveground piping to the four new clarifiers. Install booster pump and weir washer systems for all four new clarifiers. Install new aluminum walkways, grating, handrail, and stair systems to allow access to all new tanks.

Palm Bay NRWWTP Clarifier #2

Formed and placed a 110’ diameter concrete clarifier. Installed new 24” influent and effluent piping, 14” sludge piping, 6” scum piping, and new clarifier equipment. New sidewalk, stairs and a walkway to the clarifier equipment platform were also installed.

SWRF Clarifier No. 3 Orlando, FL

Forming and placing of 175’ Dia. Concrete clarifier and flow splitter box outside of structure. Installation of 54” & 30” under slab piping. Approx. 4110 CY of concrete total.

Palm Bay Lime Softening Units 1 & 2

Demo existing equipment of two lime softening units. Replace piping and install new equipment including steel fillet plates, columns, troughs, drives, and bridges. Included the addition of one Westech Aerator, leak repair of the existing concrete structures by way of injection, as well as all associated coatings of concrete and piping, required electrical, and I&C.